Project Alpha:

Logo with text "buildR3.com".

             Record of Key Dates / Milestones & Lead Times: 9: Dig Foundation Hole & Remove Excess 9—>10-15: Rain Delay & Concrete Work Lead Time 10-15-10-31: Footings Build & Material Deliveries 11-1: Inspection Approved – Footings Prepour11-4: Foundation Foot & Rock Pour12-2: Approx 28 days per Man. recommendation 4 capillary…