PROJECT ALPHA

 

  

 

Record of Key Dates / Milestones & Lead Times:

9: Dig Foundation Hole & Remove Excess

9—>10-15: Rain Delay & Concrete Work Lead Time

10-15-10-31: Footings Build & Material Deliveries

11-1: Inspection Approved – Footings Prepour11-4: Foundation Foot & Rock Pour12-2: Approx 28 days per Man. recommendation 4 capillary break (to application after concrete set)12-7 to 12-21: All ICF rebarred walls & waterproof soil side / bottom 4′

Holiday: 12-22–>12-27 & 12-30—>1-2

1-5: Radon Installation Part 1, Finalize Porch & Balcony

1-8: Construction Fence & Final Walls Waterproofing

1-9 to 1-31: Weather Stoppage

2-6: Continuous Pour / All Walls

2-8: Capillary Break Top Of Foundation

2-9: Steel Prep / Wood Removal

2-14: Wood Removal Final Concrete

2-19 & 20: Backfill and Excess Dirt Removal

2-22: Steel Set I Beams & Columns (1 Day)

2-27: Start Framing

3-29: 1st Floor & Garage Complete

5-3: PENDING

 

 