Project Alpha: 1+ Mil Hyper Home >>> Mokena
PROJECT ALPHA:
Record of Key Dates / Milestones & Lead Times:
9: Dig Foundation Hole & Remove Excess
9—>10-15: Rain Delay & Concrete Work Lead Time
10-15-10-31: Footings Build & Material Deliveries
11-1: Inspection Approved – Footings Prepour
11-4: Foundation Foot & Rock Pour 12-2: Approx 28 days per Man. recommendation 4 capillary break (to application after concrete set) 12-7 to 12-21: All ICF rebarred walls & waterproof soil side / bottom 4′Holiday: 12-22–>12-27 & 12-30—>1-2
1-5: Radon Installation Part 1, Finalize Porch & Balcony
1-8: Construction Fence & Final Walls Waterproofing
1-9 to 1-31: Weather Stoppage
2-6: Continuous Pour / All Walls
2-8: Capillary Break Top Of Foundation
2-9: Steel Prep / Wood Removal
2-14: Wood Removal Final Concrete
2-19 & 20: Backfill and Excess Dirt Removal
2-22: Steel Set I Beams & Columns (1 Day)
2-27: Start Framing
3-31: 1st Floor & Garage Complete
5-9: Exterior Sheathing & Home Wrap
6-29: 2nd Floor Completion 50%
7-31: 2nd Floor Completion 95%
9-30: Roof & Porch Framing (Guidance)
11-9: Windows In & Roofing On