100% Complete
PHONE: 555-808-5555
EMAIL: AWESOME@HOTMAIL.COM
100% Progress
February 4, 2020
March 31, 2020
9 / 9 Completed
100%
20%
AFTER FRAMING
15%
AFTER ROUGH PLUMBING / HVAC / ELECTRICAL COMPLETE
APPROVED CHANGES
AFTER DRYWALL INSTALL
15%
AFTER WALL PAINT
10%
AFTER LUXURY VINYL INSTALL
10%
AFTER DOORS & BASE TRIM INSTALLED
UPON FULL COMPLETION
22 / 22 Completed
ALL MATERIAL SELECTIONS / ELECTION
to be performed into a concise document by R3 for Design Center selection by Client
ARRIVAL
8-9AM
REMOVE VARIOUS EXISTING FRAMING
NEW WALL & CEILING FRAMING
ARRIVAL 8-9AM
ARRIVAL TIME TBA
ARRIVAL TIME 7:30 AM -9AM
ARRIVAL As Noted
ARRIVAL 8-10A
TIME TBA
R3 ARRIVAL 8-9A
ARRIVAL BY VILLAGE REQUESTS (WE WILL NOTIFY YOU OF EITHER MORNING OR AFTERNOON ARRIVAL WINDOW FOR ALL VILLAGE INSPECTORS)
ARRIVAL 8-9A
ARRIVAL 8-9A
ARRIVAL TBD
LUXURY VINYL INSTALL (2 DAYS)
ARRIVAL 8-9A
ARRIVAL 8-9A
ARRIVAL 8-9A
2 ROUNDS (2 DAYS)
NOTE: ALL TOUCH UPS AND ANY FINAL ITEMS TO BE COMPLETED ON 03-26
ARRIVAL Time TBD
TBA
NO WORK TO BE COMPLETED ON THESE DAYS
CLIENT REQUESTED = CR
R3 SCHEDULING= RS
ARRIVAL 8-10A
ARRIVAL 8-8:30A